Check before you apply. Amounts, dates and eligibility may be out of date or wrong. Confirm with the agency. About accuracy
Status checked November 26, 2026

New York water infrastructure funding

Federal, state and local grants and loans that communities in New York can use for drinking water, wastewater and stormwater projects.

26Grant programs
5Loan programs
17Can apply now

Grants and loans by what they fund

Programs that offer both appear in both columns. Includes federal programs open to this state.

InfrastructureGrants 26Loans 5Match and other help 1
Drinking water
Wastewater (sewer)
Stormwater & flood

Open nowRollingCheck agencyOpening soonAwaiting NOFONext cycle

Why timing matters this cycle

Sources [1] [2] [3] [4] [5]

Key dates, next 12 months

“Expected” dates follow last year’s cycle. Confirm them with the agency.

  1. Dec 2, 2026
    Watch
    DHSES FY2026 FMA webinar10 to 11 a.m. Registration is on the DHSES hazard mitigation page.DHSES hazard mitigation intake (FMA, HMGP, BRIC)
  2. Dec 11, 2026
    Watch
    Federal continuing resolution expiresFY2027 EPA, FEMA and USDA budgets are not final. A lapse would pause federal grant processing.
  3. Dec 17, 2026
    Deadline
    Hudson River Estuary grant applicationsCovers tributary restoration (stream crossings, dam removal) and local stewardship planning.Hudson River Estuary grants (tributary restoration and planning)
  4. Dec 21, 2026
    Deadline
    New York FMA sub-applications due to DHSES in FEMA GODHSES sends New York's application to FEMA by Feb 26, 2027.DHSES hazard mitigation intake (FMA, HMGP, BRIC)
  5. Dec 31, 2026
    Deadline
    CDBG Open Round closesLast day for Imminent Threat and Community Planning applications in the 2026 round, if funds remain.CDBG Open Round (Imminent Threat and Community Planning)
  6. Dec 2026–Jan 2027estimate
    Expected
    Typical state cutoff for FMA subapplicationsStates set their own earlier deadlines. Confirm with the state emergency management agency.Flood Mitigation Assistance (FMA), FY2026
  7. Jan 29, 2027
    Deadline
    Green Resiliency Grant applications4 p.m. through the EFC portal. $45M in Bond Act money for flood-reducing stormwater projects.Green Resiliency Grants (Environmental Bond Act)
  8. Feb 26, 2027
    Deadline
    FEMA Flood Mitigation Assistance (FY2026) deadlineState applications due to FEMA.Flood Mitigation Assistance (FMA), FY2026
  9. ~Feb–Mar 2027estimate
    Expected
    FY2028 Community Project Funding requestsEach congressional office sets its own deadline.Community Project Funding (earmarks)
  10. ~May 2027estimate
    Expected
    2027 CFA round opens (WQIP Round 23)DEC expects WQIP Round 23 to open in May 2027. NPG, Climate Smart Communities and CDBG Public Infrastructure used the same CFA in 2026.Water Quality Improvement Project (WQIP) grants
  11. May 28, 2027
    Deadline
    CWSRF financing applications and FFY2028 listingsFinancing applications, income surveys and new project listings with an acceptable engineering report are all due.Clean Water SRF, incl. hardship financing
  12. ~Late May 2027estimate
    Expected
    DWSRF listing deadline for the FFY2028 planDOH asks for listings by May. Last year's deadline was May 29, 2026, the same day as the clean water deadline.Drinking Water SRF, incl. lead service lines and LIFT grants
  13. ~Jun 2027estimate
    Expected
    EPG and GIGP applicationsBoth 2026 rounds closed Jun 12, 2026. EFC has not announced 2027 rounds.Wastewater Infrastructure Engineering Planning Grant (EPG)
  14. ~Late Jul 2027estimate
    Expected
    WIIA and IMG applicationsThe 2026 round was due Jul 27, 2026. EFC has not announced a 2027 round.Water Infrastructure Improvement (WIIA) and Intermunicipal (IMG) grants
  15. ~Late Jul 2027estimate
    Expected
    2027 CFA deadline (WQIP, NPG, CDBG Public Infrastructure)The 2026 CFA deadline was Jul 31, 2026 at 4 p.m.Water Quality Improvement Project (WQIP) grants
  16. Aug 2027
    Watch
    Draft FFY2028 CWSRF planCheck your project's category and score. Comments are due in September 2027.Clean Water SRF, incl. hardship financing

All programs

Filter by type, what it funds and whether it is open.

Federal Most federal water money reaches communities through the state programs below.

Flood Mitigation Assistance (FMA), FY2026

FEMA, through the state emergency management agency
Open now
GrantStormwater & flood
Next date
Feb 26, 2027 to FEMA. State deadlines come earlier.
Funding
$400M+ nationally, including about $20M for capability and capacity building
Who
NFIP communities in good standing with a FEMA-approved local hazard mitigation plan
Pays for
Localized flood risk reduction projects, elevation and acquisition of flood-prone properties, project scoping, planning and technical assistance.

In New York: Apply through DHSES: build the sub-application in FEMA GO by Dec 21, 2026. There is no separate letter of interest. DHSES holds a webinar Dec 2, 2026.

Last year of IIJA money for FMA.

How NEER helps: Benefit-cost analysis, H&H modeling for project scoping, repetitive loss area analysis (also earns CRS credit).

FMA Swift Current, FY2026

FEMA, through the State Hazard Mitigation Officer
Open now
GrantStormwater & flood
Next date
Deadline set for each qualifying flood disaster
Funding
$600M nationally
Who
Communities in states with a qualifying major flood disaster declaration
Pays for
Fast-tracked mitigation of repetitive and severe repetitive loss structures insured by the NFIP.

In New York: Swift Current needs a flood-related major disaster declaration. New York's most recent is DR-4839 (Oct 21, 2024, Suffolk, Lewis and Oswego counties). DHSES had posted no FY2026 Swift Current intake when checked.

Ask the State Hazard Mitigation Officer whether Swift Current was triggered for your county.

How NEER helps: Identify and rank repetitive loss structures with flood models.

Hazard Mitigation Grant Program (HMGP)

FEMA, through the state emergency management agency after a declaration
Open now
GrantStormwater & floodWastewater (sewer)Drinking water
Next date
Usually due within 12 months of the declaration. Confirm with the state.
Funding
Set as a share of each disaster’s federal assistance
Who
Jurisdictions in states with a major disaster declaration
Pays for
Cost-effective mitigation in the hazard mitigation plan: drainage upgrades, buyouts, flood warning, backup generators.

In New York: New York's most recent major disasters with hazard mitigation are DR-4825 (Tropical Storm Debby, Sep 24, 2024, 11 counties) and DR-4839 (Oct 21, 2024). None since, per OpenFEMA. Ask DHSES whether any intake remains open.

Available only after a major disaster declaration in your state.

How NEER helps: Project definition and BCA backed by sewer and stormwater models.

Building Resilient Infrastructure & Communities (BRIC)

FEMA, through the state emergency management agency
Awaiting NOFO
GrantStormwater & floodWastewater (sewer)Drinking water
Next date
FY2024–25 round closed Jul 23, 2026. FY2026 NOFO timing is under court order.
Funding
$1B for FY2024 and FY2025 combined
Who
States apply; local governments are subapplicants with an approved hazard mitigation plan
Pays for
Larger pre-disaster infrastructure projects plus capability and capacity building.

In New York: DHSES had posted no BRIC intake or dates when checked. Ask DHSES about the state's list for the next round.

FEMA restarted BRIC in March 2026 after a court order, with rewritten rules. Scope projects now so they are ready when FY2026 opens.

How NEER helps: Scoping studies and modeling to make projects application-ready.

Rolling
LoanDrinking waterWastewater (sewer)Stormwater & flood
Next date
Letters of interest accepted anytime
Funding
About $6.5B available (November 2025 notice), plus $550M through SWIFIA for state authorities
Who
Public and private borrowers; projects generally $20M+ ($5M+ for communities of 25,000 or fewer)
Pays for
Long-term, low-rate loans for up to 49% of eligible costs for water, wastewater and stormwater projects.

Suited to large utility capital programs. Can be paired with SRF financing.

How NEER helps: Capital program optimization to package projects for a WIFIA loan.

Opening soon
GrantWastewater (sewer)Stormwater & flood
Next date
FY2025–26 allotments released Apr 2026; each state sets its own call
Funding
About $80M nationally for FY2025 and FY2026
Who
Municipalities; small and financially distressed communities need no cost share
Pays for
Combined and sanitary sewer overflow control and stormwater management projects.

Ask the state SRF program how and when it will distribute its allotment.

How NEER helps: Overflow and capacity modeling to define projects.

GrantDrinking water
Next date
Through the state drinking water program
Funding
$945.7M for FY2026, the final IIJA tranche
Who
Systems serving 10,000 or fewer people, or disadvantaged communities under state criteria
Pays for
PFAS and other emerging contaminant testing, planning and treatment. No local cost share.

EPA noted some states have been slow to spend earlier EC-SDC funds, so prior-year money may still be available.

How NEER helps: Source and treatment alternatives screening with water system models.

Rolling
LoanGrantDrinking waterWastewater (sewer)Stormwater & flood
Next date
Applications accepted year-round through RD Apply
Funding
Loans up to 40 years; Jul–Sep 2026 rates were 2.875% (poverty) to 4.75% (market)
Who
Rural areas and towns of 10,000 or fewer people
Pays for
Drinking water, sanitary sewer, solid waste and stormwater drainage. Grants are combined with loans to keep user rates reasonable.

Grants are awarded alongside a loan, not on their own.

How NEER helps: Preliminary engineering reports with hydraulic models.

Public Works & Economic Adjustment Assistance

U.S. Economic Development Administration
Rolling
GrantDrinking waterWastewater (sewer)
Next date
No deadline; reviewed as received
Funding
EDA total FY2026 appropriation about $466M
Who
Distressed areas; project must be consistent with the regional CEDS
Pays for
Water and wastewater infrastructure that supports job creation, such as service to an industrial park.

Tie the project to named employers and jobs. Local match is required.

How NEER helps: Capacity analysis for new industrial load.

Community Project Funding (earmarks)

Your U.S. Representative and Senators
Opening soon
GrantDrinking waterWastewater (sewer)Stormwater & flood
Next date
FY2028 requests likely due Feb–Mar 2027 (FY2027 office deadlines were early to mid March 2026)
Funding
FY2026: $893M clean water and $715M drinking water earmarks nationally
Who
Local governments and utilities with a ready project and documented local support
Pays for
One-time grants passed through the SRF accounts and other federal accounts.

Have the project description, cost estimate and support letters ready in January. Each office sets its own form and deadline.

How NEER helps: Project sheets with modeled benefits.

Rolling
Federal projectStormwater & floodDrinking waterWastewater (sewer)
Next date
Send a letter of request to the district anytime
Funding
Cost-shared federal study and construction
Who
Non-federal sponsors such as cities and counties
Pays for
§205 small flood risk management projects; §14 emergency streambank protection; §219 water and wastewater infrastructure where Congress has authorized it.

§219 needs specific authorization in a Water Resources Development Act, so start with your congressional office.

How NEER helps: Existing-conditions flood modeling to support the request.

New York The Environmental Facilities Corporation (EFC) runs both SRFs (with DEC for clean water and DOH for drinking water) and the state water grants (WIIA, IMG, EPG, GIGP, Green Resiliency); DEC and DOS give water quality and flood grants through the Consolidated Funding Application; HCR's Office of Community Renewal runs state CDBG; DHSES handles hazard mitigation.

Clean Water SRF, incl. hardship financing

NYS Environmental Facilities Corporation (EFC), with DEC
Open now
LoanGrant (grants for hardship projects)Wastewater (sewer)Stormwater & flood
Next date
FFY2027 plan runs Oct 1, 2026 to Sep 30, 2027. Financing applications, income surveys and new listings for the FFY2028 plan are all due May 28, 2027. Draft FFY2028 plan in August 2027.
Funding
About $1.7B in interest-free or subsidized financing and grants for FFY2027. Hardship: interest-free, 30 years, no fees, up to $25M per municipality over five years. Subsidized: 50% of market rate long term; short-term interest-free on half the cost.
Who
Municipalities, including counties, cities, towns, villages, districts and public authorities
Pays for
Treatment plants, collection sewers, CSO and SSO reduction, and stormwater and nonpoint source projects.

A project reaches the Annual List only with an acceptable engineering report filed by the listing deadline. Hardship needs MHI under 80% of the regionally adjusted state MHI ($84,578 upstate, $108,536 in the lower Hudson counties), or 80–100% with poverty above 9.8%. Hardship projects may also get grants; EFC sets the amount each year, up to $25M per municipality over five years. The FFY2027 plan allocates all remaining IIJA emerging contaminant money.

How NEER helps: Engineering reports and I/I and CSO studies built on calibrated sewer models.

Drinking Water SRF, incl. lead service lines and LIFT grants

NYS Department of Health (plan and listings) and EFC (financing)
Open now
LoanGrant (principal forgiveness and state lift grants)Drinking water
Next date
FFY2027 listings closed May 29, 2026. Listings for FFY2028 are accepted on a rolling basis; DOH asks for them by May. Expected deadline late May 2027.
Funding
About $1.03B in interest-free or low-interest financing and grants for FFY2027. Hardship projects get interest-free financing; others get a rate 33 1/3% below EFC's market rate. LIFT: over $130M in state grants to 24 systems in Sep 2026 to pay off lead line loans.
Who
Public water systems; DOH sets hardship rules in its plan
Pays for
Treatment, mains, storage, interconnections, consolidation, lead service line inventory and replacement, and emerging contaminant treatment.

DOH prepares the plan and takes listings, so the engineering report must follow DOH's outline. LIFT gives priority to communities with MHI under 80% of the regionally adjusted state MHI or poverty above the state rate. DOH's site blocked our check, so confirm current hardship and lead line terms with DOH.

How NEER helps: Lead service line material prediction; water system models for engineering reports and PFAS alternatives.

GrantDrinking waterWastewater (sewer)
Next date
2026 round closed Jul 27, 2026; about $500M to 106 projects announced Oct 20, 2026. Next round not announced.
Funding
Clean water: lesser of $25M or 25% (50% up to $25M for hardship communities of 3,500 or fewer). Drinking water: lesser of $5M or 70%; PFAS above the federal MCL or 1,4-dioxane above the state MCL 70% with no cap; lead line inventory 100% up to $2M; lead line replacement 70% up to $10M. IMG: lesser of $30M or 40%.
Who
Municipalities with municipally owned sewage treatment works or public water systems. IMG needs an intermunicipal agreement and a lead municipality.
Pays for
Construction, repair and upgrades for water quality and public health, emerging contaminant treatment, CSO and SSO fixes, and lead service line work.

The 2026 application needed an engineering report, finished environmental review, a SHPO letter and a bond or authorizing resolution, and doubled as the SRF application. Projects that only serve new development are not eligible.

How NEER helps: Engineering reports and regional connection studies built on water and sewer models.

GrantWastewater (sewer)
Next date
2026 round closed Jun 12, 2026; $3.1M to 63 projects in Sep 2026. Next round not announced.
Funding
Up to $50K for an engineering report or preliminary I/I study; up to $100K for a sewer system evaluation survey required by an enforcement order. 20% local match.
Who
Municipalities with MHI of $90,000 or less (upstate regions) or $110,000 or less (Long Island, New York City, Mid-Hudson)
Pays for
The engineering report or I/I study a municipality needs before it can seek CWSRF financing.

Other grants can't count as the match. EFC's FFY2027 plan sets aside $3M for EPG.

How NEER helps: Engineering reports and I/I studies with flow monitoring and calibrated sewer models.

GrantStormwater & floodWastewater (sewer)Drinking water
Next date
2026 round closed Jun 12, 2026; $16.8M to eight projects in Sep 2026. Next round not announced.
Funding
2026 round: $15M. 50% to 90% of eligible costs, up to $3M per project, set by MHI and poverty.
Who
Green stormwater: municipalities, private entities, state agencies and soil and water conservation districts. Energy efficiency: publicly owned treatment works. Water efficiency: municipalities.
Pays for
Green stormwater infrastructure, energy efficiency and water efficiency at water and wastewater systems.

Funded from the CWSRF, so federal engineering procurement rules apply. Green stormwater projects can get up to 90% where MHI is $90,000 or less upstate or $110,000 or less downstate.

How NEER helps: Green infrastructure sizing and runoff reduction modeling.

GrantStormwater & flood
Next date
Jan 29, 2027 at 4 p.m. through the EFC portal
Funding
$45M. $1M to $10M per project, up to 90% of eligible costs. 10% local match.
Who
Municipalities as defined in the Bond Act, including counties, cities, towns, villages, districts, public authorities and tribes
Pays for
Stormwater projects that combine green and gray infrastructure to cut flooding and improve water quality in one defined drainage area.

Projects must capture at least 2,500 cubic feet of water quality volume, and either store the 10-year, 6-hour storm or show with H&H modeling that flood risk drops. Planning-only projects are not eligible, and construction can't start before award. Other state funds can't be the match.

How NEER helps: H&H modeling for the flood demonstration approach and storage sizing.

GrantDrinking waterWastewater (sewer)Stormwater & flood
Next date
No deadline. First come, first served until money runs out.
Funding
$225M ($50M set aside for rural municipalities). Up to $30M or 75% of eligible costs.
Who
Municipalities certified as Pro-Housing Communities by HCR; counties whose project supports housing there. Two awards per municipality.
Pays for
Water, sewer or stormwater capacity projects that unblock housing, from planning and design through construction.

The application needs an engineering report and environmental review. Construction should start within a year of award and the housing within two.

How NEER helps: Capacity studies showing the water or sewer constraint and the fix.

Water Quality Improvement Project (WQIP) grants

NYS Department of Environmental Conservation (DEC), through the CFA
Next cycle
GrantWastewater (sewer)Stormwater & floodDrinking water
Next date
Round 22 closed Jul 31, 2026; $246M to 139 projects announced Oct 30, 2026. Round 23 expected to open May 2027.
Funding
Round 22: at least $75M advertised. Wastewater up to $1M–$15M by subtype and population; nonpoint source up to $100K–$10M; MS4 vacuum trucks $400K; source water land $5M; salt storage $400K–$600K. 25% match of the award.
Who
Municipalities; soil and water conservation districts and nonprofits for some project types
Pays for
Wastewater treatment upgrades, nonpoint source and stormwater projects, source water land, road salt, dams, aquatic connectivity and leachate treatment.

Construction only, no planning-only projects. Wastewater projects need an engineering report attached to the CFA. Other state grants can't be the match, but SRF loans can.

How NEER helps: Engineering reports and stormwater models that quantify the water quality benefit.

GrantStormwater & flood
Next date
Round 7 closed Jul 31, 2026; $2.9M to 42 projects announced Oct 30, 2026. Next round expected with the 2027 CFA.
Funding
Up to $3M. Nonpoint source planning reports $50K–$75K; MS4 mapping $75K per municipality or $400K for a group; MS4 stormwater program planning up to $50K. 10% match.
Who
Municipalities and soil and water conservation districts; MS4 grants for regulated MS4 operators
Pays for
Planning reports that ready nonpoint source projects for construction, and MS4 system mapping and program planning.

Don't apply to NPG and WQIP for the same project. Wastewater planning goes to EFC's EPG instead.

How NEER helps: MS4 system mapping and stormwater models for planning reports.

Next cycle
GrantStormwater & flood
Next date
Round 2 closed Jun 26, 2026. No later round announced; check the agency.
Funding
Round 2: $60M. 10% match.
Who
Applicants with a Resilient NY flood study or a DEC-approved comparable study
Pays for
Floodplain and wetland restoration, berm and dam removal, right-sized culverts, stream restoration and daylighting.

Projects must come from a flood study, so check whether your watershed has a Resilient NY study first.

How NEER helps: H&H modeling to update a flood study and size culverts.

Next cycle
GrantStormwater & flood
Next date
2026 round closed Jun 26, 2026. No later round announced; check the agency.
Funding
About $39M: $20M coastal (minimum $300K) and $19M inland flooding and LWRP (minimum $150K). Up to 90% of costs; 10% match.
Who
Municipalities, nonprofits, soil and water conservation districts and state agencies. Inland projects need a relevant LWRP or DOS-funded watershed plan.
Pays for
Final design and construction of flood risk reduction, nature-based shoreline, culvert right-sizing, stormwater retrofits and green infrastructure.

Other state grants can't be the match.

How NEER helps: Stormwater and flood models for design.

Next cycle
GrantStormwater & flood
Next date
2026 round closed Jul 31, 2026. Next round expected with the 2027 CFA.
Funding
2026: at least $18M. Implementation and feasibility or design studies $35K to $2M; certification actions $10K to $200K. Up to 80% of eligible costs.
Who
Local governments, local public authorities and public benefit corporations, and Indian Nations
Pays for
Flood risk reduction feasibility and design studies, adaptation projects and climate planning actions.

Feasibility and design work for flood projects is eligible here, unlike WQIP and Green Resiliency Grants.

How NEER helps: Flood risk feasibility studies with H&H models.

Open now
GrantStormwater & flood
Next date
Dec 17, 2026
Funding
About $1.25M across four requests. Tributary restoration and resiliency $10.5K–$200K; local stewardship planning $10.5K–$50K.
Who
Local organizations and communities; each request sets its own eligibility
Pays for
Stream crossing replacement and design, dam removal, and climate adaptation and watershed planning.

Read the request for applications for applicant and match rules; the release does not list them.

How NEER helps: Culvert and stream crossing sizing with hydraulic models.

CDBG Public Infrastructure

NYS Homes and Community Renewal, Office of Community Renewal
Next cycle
GrantDrinking waterWastewater (sewer)Stormwater & flood
Next date
2026 round ran May 18 to Jul 31, 2026 through the CFA. 2027 round expected on the same CFA schedule.
Funding
About $25M. Up to $1.5M per applicant, or $2M with committed co-funding of at least 20% (USDA, EFC, WIIA, WQIP and others).
Who
Non-entitlement cities, towns and villages under 50,000 and counties under 200,000. Projects must meet a CDBG national objective, usually low and moderate income benefit.
Pays for
Water source, storage and distribution, sewer and treatment, and flood control and storm drainage.

A listing on EFC's plan does not count as committed co-funding. Lead lateral or sewer lateral work can be up to 15% of the request as an ancillary activity.

How NEER helps: Engineering reports and models that define the project.

CDBG Open Round (Imminent Threat and Community Planning)

NYS Homes and Community Renewal, Office of Community Renewal
Open now
GrantDrinking waterWastewater (sewer)Stormwater & flood
Next date
Rolling until Dec 31, 2026 or until funds run out
Funding
About $20M across categories. Imminent Threat up to $1M; Community Planning up to $50K.
Who
Non-entitlement cities, towns, villages and counties
Pays for
Imminent Threat: urgent repairs to water and sewer systems, storm drainage, flood walls and culverts. Planning: assessments that identify projects for later CDBG funding.

Imminent Threat applicants must show a serious, immediate threat and that no other funding is available. Start with OCR's pre-application.

How NEER helps: Condition assessments and planning studies.

DHSES hazard mitigation intake (FMA, HMGP, BRIC)

NYS Division of Homeland Security and Emergency Services (DHSES)
Open now
GrantStormwater & flood
Next date
FY2026 FMA sub-applications due in FEMA GO Dec 21, 2026
Funding
Passes through FEMA funds
Who
State agencies and local governments, including special districts. FMA needs NFIP good standing and a FEMA-approved local hazard mitigation plan.
Pays for
DHSES reviews sub-applications in FEMA GO and sends them to FEMA by its Feb 26, 2027 deadline.

For FMA, go straight to a sub-application in FEMA GO; there is no separate state letter of interest. Questions go to HazardMitigation@dhses.ny.gov or (518) 292-2304. OpenFEMA shows no New York major disaster since DR-4839 (Oct 21, 2024).

How NEER helps: Benefit-cost analysis and H&H modeling for flood mitigation sub-applications.

LoanMatch helpStormwater & flood
Next date
Rolling, reviewed quarterly until funds run out. Send DHSES the interest form.
Funding
1% interest. Up to 20 years after completion; up to 30 years for low-income or underserved areas.
Who
Local governments
Pays for
Loans for mitigation projects, including localized flood risk reduction, infrastructure retrofits, and the local share of FEMA mitigation grants.

Priorities include socially vulnerable areas, non-federal cost share for mitigation projects, and projects that failed a FEMA benefit-cost analysis. Past loans were mostly county culvert replacements. Terms are from the FY2024 plan.

How NEER helps: Culvert and drainage sizing with H&H models.

Local and regional County and regional cost-share programs.

GrantMatch helpStormwater & flood
Next date
No set cycle. Check the agency.
Funding
The county paid 50% of a $2.4M project in Briarcliff Manor (Jan 2025). Over $116M allocated countywide.
Who
Municipalities in Westchester County
Pays for
County funding for municipal flood control projects.

The county approves a bond act for each project and signs an intermunicipal agreement. The municipality builds the project and gives the county an easement for the bond term.

How NEER helps: Drainage studies and H&H models to define the project.

Sources

  1. CRS: FY2026 EPA water infrastructure appropriations
  2. Water Online: federal funding cliff (Aug 2026)
  3. CRS: FY2027 Interior-Environment appropriations (Oct 2026)
  4. CRS: BRIC recent developments (Jun 2026)
  5. FEMA FY2026 FMA NOFO summary (Granted, Oct 2026)
  6. American Flood Coalition: FMA
  7. FY2026 FMA Swift Current NOFO
  8. FEMA $600M Swift Current announcement
  9. Missouri SEMA Mitigation Management
  10. FEMA-4924-DR Missouri declaration map
  11. Kansas DR-4897 declaration notice
  12. GAO-26-107774: BRIC
  13. EPA WIFIA available funding
  14. EPA OSG FY2025–26 allocation memo
  15. EPA FY2026 EC-SDC allotment memo
  16. USDA Water & Waste Disposal Loan & Grant
  17. Grants.gov: EDA PWEAA (no deadline)
  18. House Appropriations FY27 member request guidance
  19. USACE CAP Section 205 fact sheet
  20. EFC, Final Clean Water SRF Intended Use Plan, FFY 2027
  21. EFC, CWSRF Hardship Financing and Additional Subsidy Eligibility Policy (effective Oct 1, 2026)
  22. EFC, Intended Use Plans and Interest Rates
  23. DEC Environmental Notice Bulletin, Final FFY 2027 CWSRF and DWSRF Intended Use Plans (Sep 30, 2026)
  24. EFC, Drinking Water State Revolving Fund
  25. DEC Environmental Notice Bulletin, CWSRF and DWSRF project listing deadline (Apr 8, 2026)
  26. Governor Hochul, $130 million in grants to inventory and replace lead service lines (Sep 2026)
  27. Governor Hochul, $200 million to help communities modernize water infrastructure (Oct 22, 2026)
  28. EFC, WIIA and IMG Grant Summary (June 2026)
  29. EFC, Water Infrastructure Improvement and Intermunicipal Grants
  30. Governor Hochul, nearly $500 million in grants for water infrastructure projects (Oct 20, 2026)
  31. EFC, Wastewater Infrastructure Engineering Planning Grants
  32. EFC, Wastewater Infrastructure Engineering Planning Grant Program Summary
  33. Governor Hochul, $80 million in grants for flood mitigation and water quality, Climate Week (Sep 21, 2026)
  34. EFC, Green Innovation Grant Program Summary (2026)
  35. EFC, Green Resiliency and Green Innovation Grants
  36. EFC, Green Resiliency Grant Program Summary (rev. Oct 1, 2026)
  37. EFC, accepting applications for $45M in flood mitigation and resiliency grants (Oct 7, 2026)
  38. EFC, Clean Water for Housing
  39. DEC, Water Quality Improvement Project Program
  40. DEC, more than $78 million available for water quality projects, applications due Jul 31 (Jun 9, 2026)
  41. Governor Hochul, $249 million awarded to 181 water quality projects (Oct 30, 2026)
  42. Regional Economic Development Councils, 2026 CFA Available Resources
  43. DEC Environmental Notice Bulletin, Resilient Watersheds Grant Round 2 request for applications (Apr 8, 2026)
  44. Governor Hochul, $100 million for climate resiliency projects through the Environmental Bond Act (Mar 30, 2026)
  45. NYS Department of State, Community Resilience and Flood Risk Reduction Grants RFA 26-OPDBA-8 (revised Jun 5, 2026)
  46. DEC, $1.25 million available for Hudson River estuary communities (Sep 24, 2026)
  47. NYS Homes and Community Renewal, Community Development Block Grant
  48. HCR, 2026 CDBG Public Infrastructure Request for Applications
  49. HCR, 2026 CDBG Open Round Request for Applications
  50. DHSES, Hazard Mitigation
  51. DHSES, FY2026 Flood Mitigation Assistance key dates and FEMA NOFO
  52. OpenFEMA, Disaster Declarations Summaries for New York since 2024 (secondary data copy)
  53. DHSES, Hazard Mitigation Revolving Loan Fund Intended Use Plan, FY2024
  54. Westchester County, flood mitigation project in Briarcliff Manor under the Storm Water Management Law (Jan 21, 2025)