- Next date
- Planning loans accepted on a rolling basis while funds last. Construction loans need a Project Priority List application: next call expected around mid-December 2026, due around mid-February 2027.
- Funding
- FFY2025 plan: about $33.9M in forgiveness. Loans at 0% interest with a 0–2.75% admin fee. Disadvantaged communities: up to 50% forgiveness and terms up to 40 years. Lead service lines: about $9.3M forgiveness, 50% for disadvantaged construction projects; 100% up to $100,000 for planning and design where local MHI is at or below 125% of state MHI. Emerging contaminants: 100% forgiveness, capped at $5M per loan. General planning: 25% forgiveness up to $100,000 per step.
- Who can apply
- Municipal and private public water systems
- Pays for
- Sources, treatment, storage and pipes; full lead service line replacement and inventories; PFAS treatment; planning, design and asset management plans.
- Tip
- Disadvantaged means MHI below the state average with user rates over 1% of MHI, or MHI at or above the state average with rates over 2.5% (24 V.S.A. § 4752). Lead line money exceeded demand, so the FFY2025 plan took lead line priority list applications at any time. Vermont deferred its FFY2025 lead line grant because earlier funds remained. Terms shown are from the FFY2025 draft plan; check the agency for the FFY2026 plan.
- How NEER helps
- Lead service line material prediction; water system models for planning and PFAS alternatives.